
Area Before Clearing
This is where the structure was to be built.
|
|

Pruning
A 'little' pruning needed to be done first.
|

Supplies
Once the area was cleared supplies were brought in. (blocks,
beams, plywood and roofing.).
|
|

Sinking the Posts
The next step was to sink about 10 posts 2" into the ground.
This usually involved chipping through limestone with a steel bar.
Once a post was in and tacked in a completely vertical position,
about 2 bags of concrete was poured and grave was added back in
to secure them.
|

Foundation and Block Parameter
A cement block parameter was then built by digging 6"-12"
into the rocky ground and pouring a cement base in which the blocks
were placed and mortared together.
|
|

Blockhouse Construction
Hurricanes threaten the Florida Keys about once a year so we needed
a hurricane resistant structure into which we can chase the birds.
It may also be used for breeding.
|

Pouring the roof
A 6" thick concrete slab roof was poured after framing it up
like this. (It was built at a very slight angle to drain away from
the house.) Most of the block walls were capped off underneath the
top row. This allowed the concrete pour to fill in the first row
of blocks at the top, providing extra support for the roof in high
winds. A few blocks were left uncapped and steel reinforced, allowing
the concrete to fill the walls. About 4000 lbs. of concrete was
used here. It was mixed on top of the adjoining roof one bag at
a time (very quickly) and shoveled down before it began to dry.
|
|

Inside the Blockhouse
This is looking through rear window and into the blockhouse and
aviary.
|

Building the frame
With a little planning, each 4*6 in the frame could be hoisted into
place and secured by just one person.
|
|

Frame from inside
Looking up at the framing from the inside.
|

Structure Frame
Here the framing is complete.
|
|

Sanding the Frame
Here I'm crawling around on the gable above the orchid area.
Everything had to be sanded dogwn before painting because the stain
might not have stuck to unsanded CDX beams that were still slightly
wet.
|
|

Paint First
2-3 coats of solid stain was hand painted on the frame before
roofing was applied. (That was after a rust resistant primer sprayed
onto all metal such as brackets and deck screws.) The structure
may outlive us, but it was probably won't be painted again.
|
|

Roof Installation
The first layer of roofing material (stucco/hardy board) is
going up here. Then came 1/2" CDX treated plywood, fiber-reinforced
roof sealant, 1/4" felt cloth, and then galvanized v-crimp
steel. .
|

Fascia
After the second layer of roofing was installed, CDX 2*4s were
sanded, stained and secured to the edge of the roof overhang to
align the ends and provide strength.
|
|

Metal Roof & Shadecloth
Felt cloth and metal roofing were then laid over the aviary roof,
and Shadecloth was stretched over the orchid house area. A lot of
care was take to eliminate any lip where the shadecloth meets the
metal roof so that leaves would not collect. |

Shadecloth
The shadecloth was fastened with nickel/copper staples to CDX
slats along the aviary roofline that had been sanded, routed and
stained. It was also glued to the concrete roof along the top of
the house. This was to allow for drainage while keeping out insects.
|
|

Slat Preparation
About 100 CDX slats were used to fasten both the screen and the
1/2" hardware cloth. They first had to have the corners of two
edges rounded with a router. Because they were not quite dry, they
were sanded with 50 grit before 2-3 coats of solid color stain was
applied. |

Screen Cutting
The slats were cut to length and laid out on a 100" roll
of Pfeiffer wire screen where sections were cut to the required
width (plus about 6").
|
|

Predrill
Slats for the screen needed to be secured to the frame with weather
resistant deck screws every foot or so. The screw holes need to be
predrilled. We chose to also counter sink them, drilling a larger
hole for the screw heads about 1/2" into the wood. (It helps
to drill the large hole when limiting its depth.) |

Screening
The screen was secured to the inside of the frame, next to the
birds. Each piece of screen was first stapled to the top of the
frame, from the middle working out without slack. Staples were about
1/2" to 3/4" from the edge so that when the slats were
flush with the inside edge, they would cover the staples. After
the top slat was secured, the bottom of the screen was stretched
slightly and stapled in the same way. This allowed application of
the bottom slat to stretch out the screen (just short of it ripping
it on the staples) as it pulled the screen out another 1/2"
or so.. (But it still didn't appear to be that tight until the sides
were done.) The first side wasn't stretched, just pulled about 1/2
more from where it was naturally laying. The final side was stapled
in such a way that the screen slack was taken away. It would then
be pulled very tight, almost like a drum, when the final slat was
applied, pulling the screen out that extra 1/2" - 3/4"
from the staple to the edge. (You get the hang of it after doing
it once.)
|
|

Flush
The screen was secured flush with the inside of the aviary frame
to reduce the birds' ability to perch on the edge and poop down the
screen or on the frame. (After 8 weeks, so far so good) |

Caulking
All cracks and spaces where insects could penetrate were filled
with a top quality silicone caulk Screw holes were filled with drywall
putty and touched up with a single coat of solid stain. The excess
screen was then trimmed away with razor blades..
|
|

Painting Hardware Cloth
Galvanized 1/2" hardware cloth was fastened to the outside
of the slats to protect the screen on the inside from predators
or flying objects. We decided to apply a coat of acrylic paint first
with a roller, primarily for aesthetics, but also to inhibit oxidation.
|

Attaching 1/2" Hardware Cloth
The painted hardware cloth was then attached to exterior of
the aviary on the slats. It was first measured and cut, and then
attached to the top with nickel/copper staples. Small holes were
predrilled, and stainless 1.5" screws with capped rubber bushings
(designed for metal roofs) were used to secure the hardware cloth
in place every foot or so.
|
|

Stucco
Two coats of stucco (scratch and finish) were then applied to
the inside and outside of both the blockhouse and the block parameter.
The limestone gravel floor was then leveled, and plants, perches,
feeders, drinkers and nests were hung.
|

Finished
The wall was torn down separating our screened patio from the
orchid area, and the boss here gives a thumbs up, signaling that
it meets with her approval and it's time to haul in the damn
birds!
There's no way this could have been
build without my beautiful wife Pech working so hard to fund the
construction and support us while I assembled it.
|
|

Tenants
The birds were then treated for mites, and their cages were
stacked and opened in the blockhouse. This is Pech upon learning
that she'd also be staying in the aviary with the birds
|